News

NEWS
EVENTS
MEETINGS
News Icon

Caller ID spoofing alert

News Icon

COVID-19 Updates and Information.

News Icon

Upcoming Oncor Tree Trimming work.

News Icon

May 2022 UPdate.

News Icon

Report coyote sighting to the City.

News Icon

Enter the Community CloseUP website photo contest!

Events Icon

Thursday, May 26 at 10:45 a.m. - Outdoor Toddler Story Time.

Events Icon

Thursday, May 26 at 3:30 p.m. - STEAM Station @ the Library.

Events Icon

Friday, May 27 at 10:45 a.m. - Outdoor Baby Story Time.

Events Icon

Saturday, May 28 at 2 p.m. - UP with Reading Kickoff Party.

Events Icon

Tuesday, May 31 at 10:45 a.m. - All Ages Story Time @ UPPL.

Events Icon

Wednesday, June 1 at 3 p.m. - Surf's UP with Reading: Mad Science.

Meetings Icon

Tuesday, June 7, 2022 - City Council Meeting

Meetings Icon

Tuesday, June 21, 2022 - City Council Meeting

VIEW ALL NEWS VIEW ALL EVENTS VIEW ALL MEETINGS

Status of various infrastructure improvement projects

January 5, 2022

The first phase of several planned improvements in Snider Plaza is well underway. With over 7,500 feet of water and 4,500 feet of wastewater lines that are nearly 100 years old, the $6.5 million project addresses all water and sewer needs in the area for the foreseeable future. The project was originally estimated to take 16 to 18 months to complete, but the City’s contractor (SYB Construction) has been able to reduce the project’s duration by seven months. As you can see in the map to the right, the sections in green have already been completed while the red are either in progress or not yet complete. Based on estimates from the contractor and City staff, all work in the area could be complete late this spring. The City is already working on the next phase of improvements, which includes paving for streets and sidewalks, landscape amenities, lighting, and fountain improvements. Final design and bidding for this upcoming phase will be a major point of emphasis for the City in 2022. 
 
Residents who live near Caruth Park have seen extensive construction to address the City‘s capacity for stormwater drainage. In 2020, the City completed the installation of a 3.5 million-gallon underground detention structure in Caruth Park. To optimize this new facility, the next phase of improvements called for increased capacity of the stormwater pipes that feed into and out of that facility. Where a single 60-inch pipe in Southwestern previously provided drainage for the area, two underground box culverts measuring 15 feet wide and 8 feet deep now provide drainage. Similarly, where a single 60-inch pipe provided drainage for Hillcrest two box culverts measuring 20 feet wide by 6 feet deep have been installed. As motorists know, this work has included extensive road closures of both Hillcrest and Southwestern. The original schedule for this $9 million project called for completion in October of 2022. SYB Construction now believes the project could be completed by April.